11.13. Gantt Chart: Adding or Removing Arrows

Applies to: @RISK 6.x/7.x, Professional and Industrial Editions

Is there a quick way to turn the display of dependency arrows on or off? I have a project with defined predecessors and successors, but none of the dependency arrows appear when I import the project to @RISK 6.

Yes, this is easy to do. In the @RISK ribbon or menu in Excel, click Project » Charts and Reports » Standard Gantt Chart. Then select or deselect "Display Links/Connectors Between Tasks".